The City of Sequim Public Works Department currently has several street, utility, and parks projects underway or nearing construction in 2011. The following are the said projects:

South 14th Avenue
DSCN0446_thumb.JPG
The "New" South 14th Avenue
December 9, 2011
South 14th Avenue will tie together Grant Road and Washington Street on the west edge of Sequim. This road will connect the Grant Road residential neighborhood and several River Road businesses to the River Road roundabout, eliminating the need for difficult turning movements onto River Road. There will be a ribbon cutting ceremony December 13, 2011 at 9:00 a.m to celebrate the opening of the road.

click here to view a slide show of the current construction processes

COMPLETED-December 9, 2011

North Blake Avenue Chip Seal
DSCN0096_thumb.JPG
The "New" N. Blake Avenue
October 12, 2011
North Blake Avenue chip seal has provided a resurfacing of the street that will extend its life for another seven years. This project has also provided an opportunity to provide a northbound bicycle path and southbound shared use bicycle/vehicle route between Washington and Fir streets. This project was completed in October.

click here to view a slide show of the construction processes

COMPLETED-October 12, 2011

South Sequim Avenue Pavement Repair
South Sequim Avenue October 10, 2011.
South Sequim Avenue October 10, 2011.
South Sequim Avenue pavement repair will be performed in the second half of October. This project, lasting less than a week depending on weather, will remove failing sections of pavement between Etta and Hemlock streets and replace them with new asphalt. There will be no final asphalt overlay of the road so it will have a patched appearance, but an overlay may be performed in 2012. The project will require flagged traffic control and may result in some delays.

click here to view a slide show of the construction processes

COMPLETED-September 28, 2011

North Rhodefer Road
North Rhodefer Road October 10,2011
North Rhodefer Road October 10,2011
North Rhodefer Road will be regraded and covered with a new crushed rock surface. Work should begin in late October or early November. Traffic control will be in place and some delays are expected.



COMPLETED-November 2, 2011

Third Avenue Sidewalks
DSCN0548_thumb.JPG
The "New" North Third Avenue Sidewalks
December 20,2011
Concrete sidewalk will be constructed on the east side of 3rd Avenue from Fir Street to the alley between Alder and Spruce streets, connecting to the existing sidewalk. This work will begin on December 12, 2011 and lasting for a couple of weeks and requires traffic control.

click here to view a slide show of the construction processes

COMPLETED-December 19,2011

Reuse Demonstration Park-Play Fields
Future Playfields at the Reuse Demonstration Park
Future Playfields at the Reuse Demonstration Park
Playfields being constructed by Sequim Family Advocates in the Reuse Demonstration Park are nearing completion. The playfields will provide opportunities for soccer and other sports.

click here to view a slide show of the construction processes.

COMPLETED-November 29, 2011

South Sequim Avenue Water Line
Replacement of an asbestos concrete water main under Sequim Avenue from Bell Street to just north of Washington Street is planned for 2011. The project will also upsize the line from 6” to 10” to allow for increased future capacity.

Brackett Road Pathway
DSCN0566_thumb.JPG
The "New" Brackett Road Pathway
December 27,2011
A six-foot wide asphalt pathway will be constructed on the south side of Brackett Road extending westerly to Priest Road. This pathway will allow pedestrians to travel safely along Brackett road. This work will begin December 12, 2011 and expected to be finished by the end of the week (December 16, 2011)

click here to view a slide show of the construction processes

COMPLETED-December 14, 2011