August 2014
August 4 - 8, 2014
concrete pour on east side of bldg
Crews pour the concrete slab on the east side of the building.
Lydig Construction will be working on the following this week:

1) Install irrigation sleeving
2) Continue mechanical, electrical, and plumbing underground work on west side of building
3) Slab preparation and reinforcement on west side of building
4) Place west side concrete slab on grade on Thursday (8/7)
5) PUD continuing power pole relocation work and removal of existing poles

The alley will remain closed for the foreseeable future until bollards are installed around the new electrical transformers. 

August 11 - 15, 2014
lobby floor is poured
Crews pour the tinted concrete for the lobby floor.
Lydig Construction will be working on the following:

1) Slab on grade edge form removal
2) Structural steel building erection
3) PUD removal of existing poles and cleanup

The alley will remain closed for the foreseeable future until bollards are installed around the new electrical transformers. 

August 18-22, 2014
steel erected for first floor
Steel is erected for the first floor of the building.
Lydig Construction will be working on the following: 

1)  Structural steel building erection
2)  Steel decking installation

The alley will remain closed for the foreseeable future until the City installs bollards around the new electrical transformers.

August 25 - 29, 2014
steel structure
Construction crews continue to install the steel structure of the building.
Lydig Construction will be working on the following:

1) Structural steel building erection
2) Steel decking installation

The alley will remain closed for the foreseeable future until the City installs bollards around the new electrical transformers.