October 2014
October 6 - 10, 2014
wall framing
Crews continue wall framing.
Lydig Construction will be working on the following:

1) Wall framing on the first floor continues
2) Rough-in on the first floor for mechanical and electrical systems
3) Installation of metal roofing

The alley will remain closed for the foreseeable future until bollards can be installed around the new electrical transformers.

October 13 - 17, 2014
second story framing to begin
Second story interior wall framing to begin.
Lydig Construction will be working on the following:

1) Wall framing on the first floor continues
2) Interior wall framing on the second floor to begin
3) Rough-in on first floor for mechanical and electrical systems
4) Installation of metal roofing and membrane roofing

The alley will remain closed for the foreseeable future until bollards can be installed around the new electrical transformers.

October 20 - 24, 2014
exterior wall prep
Preparation begins for exterior walls.
Lydig Construction will be working on the following:

1) Wall framing on the first and second floor
2) Rough-in on first floor for mechanical systems
3) Installation of metal roofing and membrane roofing

The alley will remain closed for the foreseeable future until bollards can be installed around the new electrical transformers.

October 27 - 31, 2014
roofing work
Crews work to install the metal roofing and membrane roofing.
Lydig Construction will be working on the following this week:

1) Continue wall framing on the first and second floor
2) Rough in on the first floor for mechanical and electrical systems
3) Installation of metal roofing and membrane roofing
4) Excavation and grading of sidewalks and parking lot areas

The alley will remain closed for the foreseeable future until bollards can be installed around the new electrical transformers.