January 2015
January 12 - 16, 2015
interior insulation
Interior insulation and drywall has begun.
Lydig Construction will be working on:

1) Hanging drywall and insulation on the first and second floors
2) Rough-in on second floor for mechanical and electrical systems
3) Installation of hardi-panels, metal siding, and sheet metal work
4) Transit parking lot asphalt paving (weather permitting)

The alley will remained closed for the foreseeable future until bollards can be installed around the new electrical transformers.

January 19 - 23, 2015
lobby windows
Crews install the windows on the Civic Center lobby.
Lydig Construction will be working on:

1) Hanging drywall and insulation on the first and second floor
2) Painting walls on the first floor
3) Rough-in on second floor for mechanical and electrical systems
4) Installation of hardi-panels, metal siding and sheet metal work
5) Transit parking lot asphalt paving (weather permitting)

The alley will remained closed for the foreseeable future until bollards can be installed around the new electrical transformers.

January 26 - 30, 2015
interior door frames
Interior door frames are being painted.
Lydig Construction will be working on:

1) Hanging and taping drywall on the first and second floor
2) Painting walls and door frames on first floor
3) Rough-in on second floor mechanical and electrical systems
4) Installation of hardi-panels, metal siding, and sheet metal work
5) Transit parking lot asphalt paving (weather permitting)

The alley will remained closed for the foreseeable future until bollards can be installed around the new electrical transformers.